Owner : |
PTT Public Company Limited |
Contractor : |
Sinopec-TRC Joint Venture |
Work Value : |
Baht 4,532.61 million + USD 103.40 million |
TRC’s Work Portion : |
Approximately 30% (Approximately of Baht 1,641.58 million) |
Scope of Work : |
EPC of a new pipeline approximately 112 km. of 28 inch diameter main transmission pipeline from Saraburi to Nakhon Ratchasima EPC new 6 Block Valve Stations and Launcher 1 receiving Station |
Work Location : |
Along Highway No.2 (Mittraphab Road) |
Work Period : |
Nov 2013 - Jan 2017 |